Photos from: Drop 5 Nearing Completion, Water Expected to be Flowing Soon




It's been 19 weeks since the catastrophic Drop 5 failure on the Milk River Diversion. Work is nearly done on the Drop 5 repairs and the final work is being completed at the beginning of the diversion. Pictures above is the Drop 1 site. "Reclamation did a project like this on Drop 3 and it has held up very well. Drop 1 walls should be poured towards the end of next week and then the top of the walls will be our last pour maybe on the 7th or 8th (of October). At this point we can turn on the water," stated Project Manager, Jennifer Patric.