Work on St. Mary's Repairs starting to take shape

The roughly 18,000 people that rely on water made possible by the St. Mary's Diversion and Milk River Irrigation Projects got a bit of good news this week. Jennifer Patrick, the Project Manager for the Milk River Irrigation Project (MRIP) Joint Board of Control said "As of today, rough numbers, Drop 2 is approximately 85% complete and construction will slow down to focus on catching up Drop 5 so the intake's concrete canal liner can be installed simultaneously to cut down on mobilization costs. The liner installation on both structures is scheduled to start September 21st. Crews have been give...