Work on St. Mary's Repairs starting to take shape

 

September 9, 2020

Drop 2

The roughly 18,000 people that rely on water made possible by the St. Mary's Diversion and Milk River Irrigation Projects got a bit of good news this week. Jennifer Patrick, the Project Manager for the Milk River Irrigation Project (MRIP) Joint Board of Control said "As of today, rough numbers, Drop 2 is approximately 85% complete and construction will slow down to focus on catching up Drop 5 so the intake's concrete canal liner can be installed simultaneously to cut down on mobilization costs. The liner installation on both structures is scheduled to start September 21st. Crews have been...